Tragsa Opens Tender for 430 kW Solar Installation at El Ejido WWTP
- Energy Box
- Aug 26, 2024
- 1 min read
The total contract value is 265,970 euros, with bids accepted until 13 September and a project execution period of 9 months.
Tragsa has issued a tender for the supply and installation of a 430 kW photovoltaic system as part of the project to enhance the use of reclaimed water at the El Ejido Wastewater Treatment Plant (WWTP) in Almería.
The contract, valued at 265,970 euros, is open for bid submissions until 13 September. The project is expected to be completed within 9 months.
The photovoltaic installation will consist of 876 modules, each with a capacity of 550 W, distributed across five three-phase inverters—four with a capacity of 100 kW each, and one with 30 kW. The inverters will be installed near the photovoltaic array and close to the connection point with the main low-voltage panel.
The system's modules, organized in series of 20 and 24, will be electrically connected in strings. These modules will be mounted on self-supporting prefabricated concrete structures in a 2H configuration on the ground, with an azimuth angle of 3° west and a tilt of 20°. The modules will be arranged in rows two modules wide, with a 2-meter gap between each row.
This project is funded through the Recovery, Transformation, and Resilience Plan.
Comments