Over 85 GW of renewables in Brazil request deadline extension

Brazilian power sector regulator Aneel has received applications for around 85.4 GW to be included in the provisional measure (MP) 1212/2024, which extends benefits to renewable generation sources.

The combined capacity comes from 1,983 energy plants, either with licences in place or in the process of obtaining them from the regulatory agency, Aneel said on Monday.

The measure gives renewable energy projects a further 36 months to start commercial operation of all their generating units. Thus, they qualify for discounts on the tariffs for the use of the transmission and distribution systems (TUST/TUSD).


The majority of the registered applications (65.7 GW) are associated with solar plants. More details on the subject are available in the table below.

Comments


c7d84ead762b77f7461506cdffba58c8.jpg

Related News

白.png
  • Facebook
  • LinkedIn
  • LinkedIn
白.png

                                       is a vertical media company dedicated to the Renewable Energy. we are one of the largest influential media in the world.

To enhance the business cooperation across the land and inland and to promote green energy, ENERGY BOX EVENTS are held around the world such as Pan Europe, Africa & Middle Eats, LATAM and Asia. Up to date, we have had 30+ events on record across the world. We are committed to subverting the traditional media marketing model, inspiring a unique and professional customized team. And not only that, there exist sales consulting, projects development, financing, Webinar, meetings, interviews and peer to peer services.

©2020-2025 Produced by Energy Box.  

bottom of page