Prosolia, Grenergy advance battery storage projects in Portugal and Spain

Prosolia Energy has commissioned a 60 MWh solar-plus-storage project in Portugal, while Grenergy has secured €100 million ($114 million) in financing for a 618 MWh standalone battery energy storage system (BESS) project in Spain.


Prosolia Energy has started operation of a battery energy storage system at its Albispark PV plant in Castelo Branco, central-eastern Portugal.


The project combines a 34.4 MWp solar installation with a 15 MW battery system offering 60 MWh of storage capacity, connected directly to the 150 kV transmission grid. According to Prosolia, it is one of the largest operational hybrid solar and storage facilities in Portugal.


The battery system was supplied by Trina Storage and includes monitoring and energy management systems designed to optimize the combined operation of the solar plant and storage facility, according to Prosolia.


The project was selected under Portugal’s Recovery and Resilience Plan (PRR), through the C21-REPowerEU program, which aims to increase grid flexibility and support greater renewable energy integration.


Prosolia said Albispark is its first international large-scale hybridization project with storage and marks the beginning of a strategy to add BESS systems to its European renewable energy portfolio.


The company plans to replicate the model in other European markets, including Italy.


Separately, Grenergy has secured a €100 million senior non-recourse financing package, including credit facilities, for its Oviedo standalone battery storage project in Spain.


The financing was provided by Banco Santander and Sumitomo Mitsui Banking Corporation (SMBC) and represents, according to Grenergy, the first financing of this type for an independent BESS project in Spain.


The project reached another milestone in February with the signing of Spain’s first financial tolling agreement for a standalone storage system. The 10-year agreement, beginning in 2028, was signed with an international investment-grade energy company.


Construction has already started on industrial land next to the La Estrecha electrical substation in La Corredoria, Oviedo, allowing direct connection to the electricity grid.


Grenergy expects the facility to begin operations in the first half of 2027. The project forms part of the company’s Greenbox standalone storage platform, which currently includes nearly 30 GWh of projects across six European markets.

 
 
 

Comments


c7d84ead762b77f7461506cdffba58c8.jpg

Related News

图片1.png

1000K+

Global Subscribers

图片4.png

100+

Global

Events

图片2.png

3K+

Global Partners

图片3.png

60+

Countries

白.png
白.png

                                       is a vertical media company dedicated to the Renewable Energy. we are one of the largest influential media in the world.

To enhance the business cooperation across the land and inland and to promote green energy, ENERGY BOX EVENTS are held around the world such as Pan Europe, Africa & Middle Eats, LATAM and Asia. Up to date, we have had 30+ events on record across the world. We are committed to subverting the traditional media marketing model, inspiring a unique and professional customized team. And not only that, there exist sales consulting, projects development, financing, Webinar, meetings, interviews and peer to peer services.

  • Facebook
  • LinkedIn
  • LinkedIn

©2019-2026 Produced by Energy Box.  

bottom of page